Lee Begole Drive Extension – Phase 1
Please note: due to the nature of road construction, inclement weather, or other unforeseen circumstances, dates and times may vary. Thanks for your patience as we work to improve our roads.
Updated: August 24, 2026
Start: September 2026
Current Status: Pending
Projected End: Fall 2027
Project Jurisdiction: City of Novi
Description:
As part of the Public Safety Buildings initiative and the new Public Safety Headquarters project, Lee Begole Drive is being reconstructed to connect Crescent Boulevard to the north and Grand River Avenue to the south. This road will provide a direct, efficient route for emergency vehicles while reducing potential delays from traffic congestion.
Phase 1 of the project includes a water main extension, new concrete storm sewer, new curbed asphalt roadway with sidewalk, and a roundabout at the Lee Begole Drive and 11 Mile Road intersection.
For more information on the Public Safety Buildings project, please visit cityofnovi.org/psbuildings.
Traffic Control/Detours:
Once the project begins, the Recycling Center on Lee Begole Drive will be closed, and 11 Mile Road will be open to local traffic only.
Progress:
8/24/2026: Preconstruction meeting.