History
September 28, 2019
The GRAND OPENING COMMUNITY WALK at the ITC Corridor Trail was a great success. Many residents showed up and were able to walk, bike, or ride the completed ITC Corridor Trail.
August 23, 2019
The installation of 2,000 feet of boardwalk is complete and the full trail is nearing completion.
Aug. 1, 2019
Asphalt has been laid north of 10 Mile Road and final grading south of 10 Mile will be done soon. Boardwalk is nearly complete.
July 12, 2019
The wet spring caused significant delays in the construction of the trail between 9 Mile and 11 Mile Roads. Crews are working on completing the boardwalk installations and anticipating final coats of asphalt to be laid in late July.
August 24, 2018
March 21, 2018
Preparation work began on the Nine Mile-to-11 Mile Road Phase (formerly Phase 1B & 2) running from Nine Mile and Garfield Roads north to 11 Mile and Medilodge Connector. Work will begin at the southwest corner of Nine Mile and Garfield Roads – at the site of the future ITC Trailhead Park – with some tree removal.
October 2017
The ITC CSP Trail running from Eight Mile at southeast corner of ITC Community Sports Park north to the northeast corner of ITC CSP was completed.
Fall 2016
Phase 3B is complete, continuing along St. John Providence Park Hospital’s southern border from Medilodge Connector to Beck Road.
August 23, 2016
Phase 1A of the trail is fully complete, with the boardwalk open between ITC Community Sports Park and running northeast to Nine Mile and Garfield Roads.
June 10, 2016
Phase 1A boardwalk support poles were installed as part of the path running from ITC Community Sports Park northeast to Nine Mile and Garfield Roads.
2013
Maybury Connector was completed at Eight Mile by the Road Commission for Oakland County.
Phase 3A (ie. Medilodge Connector) was completed, running north from 11 Mile (east of Wixom Road) about 1/3 of a mile and then east to St. John Providence Park Hospital boundary.