Village Wood Road Reconstruction (Cranbrooke Drive to Haggerty Road)
Updated: February 19, 2026
Start: April 2026
Status: Pending
End: September 2026
Jurisdiction: City of Novi
Description:
The City’s contractor will reconstruct Village Wood Road from Cranbrooke Drive to Haggerty Road with new asphalt, concrete curb and gutter, enclosed ditches, improved storm sewer network, and a new 6-foot wide concrete sidewalk along the north side of the road.
Detours:
Eastbound traffic will be maintained at all times, no matter which side of the road is being worked on. Westbound traffic will be detoured south on Haggerty Road, west on 9 Mile Road, north on Cranbrooke Drive, and back to Village Wood Road for the duration of the project.