8 Mile Road to 9 Mile Road

Please note - due to the nature of road construction, inclement weather or other unforeseen circumstances, dates/times may vary. Thanks for your patience as we work to improve our roads.

Updated: July 24, 2025
Start: April 15, 2025
Current Status: In Progress
Projected End: Winter 2026
Project Jurisdiction: Road Commission for Oakland County

Progress: 

7/24/2025: Utility work is ongoing. Phase 2 work between 8 Mile Road and Allen Drive is expected to start in mid-August.

7/8/2025: The Phase 1 utility work has started with Consumers relocating their infrastructure. DTE has also begun construction.

6/10/2025: RCOC has submitted final plans to the State (Michigan Department of Transportation) for a July 11th bid letting. The Phase 1 utility work has started with Consumers relocating their infrastructure. DTE is likely to start in the summer.

5/1/2025: RCOC will submit final plans to the State (Michigan Department of Transportation) by the end of May for a July 11 bid letting. They hope to have a contractor on board for a Phase 2 closure from 8 Mile Road to Allen Drive by this fall and completed by November of this year. The Phase 1 utility work will start with Consumers relocating their infrastructure in mid-May. DTE is likely to start in the summer.

Description:

The Road Commission for Oakland County (RCOC), in partnership with the cities of Novi and Northville, will rehabilitate and reconstruct Novi Road, from 8 Mile to 9 Mile Roads.

Phase 1 - relocate utilities (DTE, Consumers, AT&T, etc.)
Phase 2 - reconstruct the 'curve' between 8 Mile Road and Allen Drive in the summer/fall of 2025
Phase 3 - rehabilitate the remainder of Novi Road from Allen Drive to 9 Mile Road.

There are also plans to add a continuous center left-turn lane throughout this entire section of Novi Road, as well as installation of a High-Intensity Activated Crosswalk or HAWK pedestrian signal just north of Galway Drive.

Road Closures/Detours:

Phase 1 - there will be intermittent lane closures specific to the various utility companies.
Phase 2 - will be a hard, full closure of Novi Road at 8 Mile and again at Allen Drive.
Phase 3 - the contractor will maintain one-way, southbound traffic only. Northbound traffic will be detoured to Haggerty, 10 Mile and back to Novi Road.

Novi Road Phase 2 Detour Map

Since this is an Oakland County project, call RCOC’s Department of Customer Services at 877-858-4804 or send an email to dcsmail@rcoc.org or visit the RCOC Website www.rcocweb.org for more information.