Updated: 5/14/24
Start: 5/2/24
Current Status: Complete
End: May 13, 2024
Project Jurisdiction: Great Lakes Water Authority
Description
GLWA is continuing the second phase of significant infrastructure improvements in the area of 8 Mile Rd near the Farmington Hills, Northville, Novi, and Livonia borders.
GLWA will install a 54-inch transmission main across 8 Mile Rd. near the I-275 bridge and restore the section of roadway within this work area. This is the last section of the 7.5 miles of transmission main to be installed between 14 Mile Rd. and 8 Mile Rd. as a part of the 54-inch transmission main project.
Road Closure
This project is complete and there are no associated road closures or detours.