Updated: 8/19/24

Start: 8/8/24
Current Status: In Progress
Projected End: August 29, 2024
Road Jurisdiction: City of Novi

Description

The City of Novi’s contractor will perform a Pavement Preservation Overlay (PPO) of Beck Road between 9 Mile Road and 11 Mile Road. This is a fast-paced pavement rehabilitation method to extend the road's life.

Road Closure

Beck Road will always remain open to two-way traffic during construction.

Detour

There is no detour at this time.