At the City Council meeting held on May 21, 2018, a long-term use agreement was approved with the Novi Community School District for the property on the west side of Beck Road and the south side of 11 Mile Road that is currently undeveloped and vacant. The agreement allows the City to make improvements and maintain the land as public park land, open for use by the general public, and not for private operation. No indoor recreation is permitted, and no permanent structures are allowed or planned, except for any storage or maintenance structures agreed upon by the City and the School District.

The City plans to use and develop the property, now known as Bosco Fields, for multi-purpose sports, athletic, and recreational fields with related amenities. It also includes parking areas and access roads off of Beck Road and off of 11 Mile Road. The final design includes 13 soccer fields of four sizes, including 4v4, 7v7, 9v9 and 11v11.

Bosco Map
 

Amenities (coming soon)

Open Greenspace  
Portable Toilets     Portable Toilets  
Soccer

History

October 31, 2019

The contractor has been working on placing topsoil, seeding, tree planting and low-point repairs to the fields. Final work before winter will include planting the last remaining trees, cleanup and final touch-ups throughout the site, remaining sidewalk at old entrance to the property, and signage and pavement markings. The fields are expected to open for use in fall 2020.

August 20, 2019

Irrigation has been installed and new trees have been planted along a berm on Beck Road
Bosco Fields

August 12, 2019

August 1, 2019

Pipe installation and grading are under construction to ensure proper irrigation for the fields.
Bosco Fields

July 11, 2019

The drainage structure and storm sewer have been completed, and four fields have been set to subgrade. Site grading and underdrain, parking lot and sidewalk work all continue. A new sidewalk has been installed along Beck Road.Bosco Fields

June 2019

Development began in spring 2019 but has been delayed by several weeks due to the weather. Completed work includes drainage structures and storm sewer and four fields have been set to subgrade. Planned work in July includes stripping topsoil and site grading, underdrain and parking lot and sidewalk concrete work. The goal is to have the fields available for use in spring 2020.

Bosco Drone Vieww