I-96 Transportation Study
 The Michigan Department of Transportation (MDOT) is
conducting a survey regarding the I-96 Corridor Study that
is being co-sponsored by the City of Novi.
This project includes a major land use and
transportation study of the greater I-96 corridor from
I-275 to Wixom Road bounded by Twelve Mile Road and
Grand River Avenue. The project will incorporate
cooperative efforts with MDOT, RCOC, and the City of
Wixom while taking advantage of major private investment
relationships with Providence Hospital, Twelve Oaks
Mall, Rock Financial Showplace and others. The study
will address road access, beautification and widening
improvements for traffic safety and economic
development. The corridor is high value to the region
and the City of Novi. MDOT has high interest because of
the volume and congestion on the freeway (average daily
traffic counts of 132,300 on I-96 east and
westbound). For the City of Novi, the corridor
represents the main thoroughfares of Grand River Avenue,
I-96, and Twelve Mile Road which residents and commerce
rely upon daily and which are all in need of upgrades.
By carefully studying this key area of the community,
the City’s future is better planned for, via the Master
Plan for Land Use, the Capital Improvement Plan, and
other tools used to forecast and guide future
development. The study's final report will be
submitted to the City of Novi in December 2010.
~~~~~~~~~~
|
|
Road Construction
See list of construction projects
listed below.
July 15, 2010 Update
Projects Overview Michigan Department of
Transportation (MDOT) Continues improvements to I-96/696
Ongoing Ramp Closures
NB M-5 ramp to WB I-96 Motorists are directed to
remain on northbound M-5, exit at 12 Mile and reenter southbound M-5
to take the southbound M-5 ramp to westbound I-96.
SB
Novi Road to WB I-96 On Ramp Traffic is directed to
continue south on Novi Road, travel west on Grand River, and enter
I-96 at Beck Road. Ramp
access to Fountain Walk Drive will remain open.
ROAD CONSTRUCTION IN FARMINGTON
HILLS IMPACTING NOVI
COMMUTERS
Grand River Avenue
from Haggerty Road to 10 Mile Road Motorists will
experience some weekend closures on Grand River at the I-275
overpass. Weekend closures will be identified in advance by
utilizing an on site portable message board. All thru traffic will
be detoured around the construction zone to10 Mile Road. Access to
businesses west of the I-275 overpass will be maintained via
Haggerty Road and access to businesses east of the I-275 overpass
will be maintained from 10 Mile/Grand River until early September.
Grand River Avenue will remain
open during construction with occasional weekend closures.
CITY OF NOVI PROJECT UPDATE
Novi Way and Ten Mile Road
Intersection (Civic Center west entrance)
improvements will include widening northbound Novi Way to add a
dedicated right turn lane, adding a right turn lane for eastbound
Ten Mile Road, adding street lighting for the intersection,
improving sidewalk ramps to comply with Americans with Disabilities
Act (ADA) requirements, and upgrading the traffic signal and
pedestrian crossing. The completed project will significantly
improve motorist and pedestrian safety at this busy intersection.
Completion is slated for August.
Nine Mile Road Rehabilitation
The Nine Mile
project (from Novi to Taft Roads)
is now complete and open for traffic.
CITY OF NOVI ANNUAL ROADWAY CAPITAL PREVENTIVE MAINTENANCE
PROJECT
Wixom Roads Update
Meadowbrook Road from Grand River to the I-96 bridge, and Wixom Road
from 11 Mile to Island Lake Drive are still under construction. From
July 21st to July 23rd, Wixom Road will undergo asphalt patches,
joint sealing, over banding and topping with asphalt. Signs and
flaggers will be placed at several different locations. Traffic will
be allowed through the work zone, although long delays are expected.
Motorists are encouraged to
seek alternate routes during the Meadowbrook and Wixom Road
construction.
Construction Projects
These dates and projects are all tentative depending upon many
variables including weather, funding etc.
|
Project Name |
From |
To |
Responsible Agency |
Estimated Project Start |
Estimated Project
Completion |
Remarks |
I-96 Bridge Reconstruction and Novi Ramp Reconstruction
|
Taft
|
Novi
|
MDOT
|
March 2010
|
November 2010
|
|
Neighborhood Street Reconstruction
|
N/A
|
N/A
|
City of Novi
|
April 2011
|
July 2011
|
Construction is being deferred to 2011 to
align projects with road funding cash flows.
|
Nine Mile Road Rehabilitation
|
Novi
|
Taft
|
City of Novi
|
May 2010
|
July 2010
|
The final component of a Federal Economic Stimulus Project.
Project includes the repaving of Nine Mile Road between Novi
Road and Taft Road. The road will remain open to traffic during
construction.
|
Ten Mile Road and Novi Way Intersection Upgrades (at Novi Civic
Center)
|
N/A
|
N/A
|
City of Novi
|
June 2010
|
August 2010
|
The project includes the addition of a right turn lane to
eastbound Ten Mile Road and a right turn lane for northbound
Novi Way. It also includes replacement of the existing traffic
signal, pedestrian signals, and sidewalk ramps to bring the
intersection into compliance with current standards. The project
is primarily funded by a federal safety grant. Ten Mile Road
will remain open to traffic during construction.
|
Novi Road Signal and Pedestrian Upgrades
|
Twelve Mile
|
Grand River
|
RCOC
|
July
2010
|
October
2010
|
The project includes the reconstruction of the traffic signals
as mast arms at Novi Road and the following intersections:
Crescent Blvd, West Oaks Dr, and the Twelve Oaks north entrance.
The project also includes sidewalk ramp construction and
improvements at each intersection to meet accessibility
requirements. The project is partially funded by the American
Recovery and Reinvestment Act (ARRA) stimulus funds and the Road
Commission for Oakland County.
|
2010 Pathway Program (various locations)
|
|
|
City of Novi
|
July 2010
|
September 2010
|
The project includes the construction of pathways along the
following streets: Willowbrook Drive (Oaktree to Guilford), Ten
Mile Road (Hampton Hill to Myrtle) and a pedestrian crossing of
Ten Mile at Nilan.
|
Novi Road Link Project
|
Main Street
|
Ten Mile
|
RCOC
|
Fall 2010
|
Fall 2011
|
Project is scheduled for construction in late 2010 through 2011
and includes the widening of Novi Road from Ten Mile To Main
Street to five lanes with a new bridge over the CSX railroad.
|
|

|