Pontiac Trail Sidewalk (Beck Road to West Park Drive)

The City's Walkable Novi Committee has identified this sidewalk/pathway as a high priority segment, due to the close proximity of several large apartment complex's and a middle school (Geisler Middle School). The City will be constructing a 6-foot wide concrete sidewalk along the south side of Pontiac Trail, from Beck Road to West Park Drive.

No detours will be needed for this project. Most of the work will be conducted off the shoulder of the Pontiac Trail roadway. Motorists may expect some delays under flag control as trucks are entering and leaving the work area.

Mattioli Cement Company was selected for this project. A bulk of the tree removals within the proposed alignment of the sidewalk will be removed the week of June 4th with more removals and course grading the following week.

Date of Completion: August 15, 2018