13 Mile Road Rehabilitation (Novi to Meadowbrook Roads)

The City of Novi has identified this segment of roadway as a high priority section for rehabilitation. Along with this much needed improvement, this project will include added or lengthened left turn lanes as well as widened through lanes to allow better traffic flow.

For the duration of the project, motorists can only travel eastbound on 13 Mile Road (from Novi Road to Meadowbrook Road). Westbound travel will be closed at Meadowbrook Road. The posted detour will be Meadowbrook Road (south) to 12 Mile Road (west) to Novi Road (north).

City Council awarded this project to Hutch Paving, Inc. at the May 21st meeting. Once contracts are finalized and a majority of the SAD-179 Vistas project (mentioned above) is complete, the contractor will begin construction on this segment. Estimated start will be after July 1, 2018.

Projected/Estimated Date of Completion: August 31, 2018